Haiti Relief & Reconstruction Watch

Haiti Relief & Reconstruction Watch

Haiti: Relief and Reconstruction Watch is a blog that tracks multinational aid efforts in Haiti with an eye towards ensuring they are oriented towards the needs of the Haitian people, and that aid is not used to undermine Haitians' right to self-determination.

The U.S. Agency for International Development Inspector General (IG) last week released an audit of a program to provide loans to businesses in Haiti (available here). The audit is just the latest report from the IG to find significant problems with USAID’s programs in Haiti, following previous findings regarding cash-for-work programs, shelter provision, food aid and USAID’s largest contractor, Chemonics. The Associated Press’ Trenton Daniel reports that: An audit of a U.S. Agency for International Department program that aimed to boost Haiti's economy by providing loans to businesses has found that the program failed to award loans to intended targets, train workers and keep accurate records.The aim of the audit released in late February by USAID's Office of the Inspector General was to see whether a USAID loan program was indeed introducing lending practices to overlooked areas and borrowers, particularly in the areas of agriculture, construction, tourism, handicrafts and waste management. Most of the loans were supposed to go toward women, first-time borrowers and small- and medium-sized enterprises. The loan program provided some $37.5 million in guarantees, of which just over $19 million in guarantees have been extended. According to publicly available data, only about a quarter went to woman-owned businesses, less than 30 percent went to first-time borrowers, and 75 percent were concentrated in the West department, though these numbers likely overstate the reality on the ground. In addition to many other problems, the audit found that “the key monitoring data was outdated, incomplete, or inaccurate,” for example, information on whether the recipient was a first-time borrower was “recorded incorrectly 41 percent of the time.”The focus of the audit, Daniel reports, was the four largest of the seven guarantees, “worth $31.5 million,” of the $37.5 million total. Of these Daniel notes that two were made after the 2010 earthquake: They were a Haitian bank named Sogebank, a Haitian development finance institution named Sofihdes that USAID helped create in 1983 and an agriculture-focused outfit named Le Levier Federation.The audit found that few women and first-time borrowers received loans and lenders didn't make much effort to work with them. And while the loans were intended to target “development corridors,” Daniel notes, Instead they stayed in the Port-au-Prince area.Ninety percent of Sogebank's loans were confined to the capital and the bank didn't give loans to other parts of the country. Some 81 percent of the Sofihdes loans were in Haiti's capital.
The U.S. Agency for International Development Inspector General (IG) last week released an audit of a program to provide loans to businesses in Haiti (available here). The audit is just the latest report from the IG to find significant problems with USAID’s programs in Haiti, following previous findings regarding cash-for-work programs, shelter provision, food aid and USAID’s largest contractor, Chemonics. The Associated Press’ Trenton Daniel reports that: An audit of a U.S. Agency for International Department program that aimed to boost Haiti's economy by providing loans to businesses has found that the program failed to award loans to intended targets, train workers and keep accurate records.The aim of the audit released in late February by USAID's Office of the Inspector General was to see whether a USAID loan program was indeed introducing lending practices to overlooked areas and borrowers, particularly in the areas of agriculture, construction, tourism, handicrafts and waste management. Most of the loans were supposed to go toward women, first-time borrowers and small- and medium-sized enterprises. The loan program provided some $37.5 million in guarantees, of which just over $19 million in guarantees have been extended. According to publicly available data, only about a quarter went to woman-owned businesses, less than 30 percent went to first-time borrowers, and 75 percent were concentrated in the West department, though these numbers likely overstate the reality on the ground. In addition to many other problems, the audit found that “the key monitoring data was outdated, incomplete, or inaccurate,” for example, information on whether the recipient was a first-time borrower was “recorded incorrectly 41 percent of the time.”The focus of the audit, Daniel reports, was the four largest of the seven guarantees, “worth $31.5 million,” of the $37.5 million total. Of these Daniel notes that two were made after the 2010 earthquake: They were a Haitian bank named Sogebank, a Haitian development finance institution named Sofihdes that USAID helped create in 1983 and an agriculture-focused outfit named Le Levier Federation.The audit found that few women and first-time borrowers received loans and lenders didn't make much effort to work with them. And while the loans were intended to target “development corridors,” Daniel notes, Instead they stayed in the Port-au-Prince area.Ninety percent of Sogebank's loans were confined to the capital and the bank didn't give loans to other parts of the country. Some 81 percent of the Sofihdes loans were in Haiti's capital.

An op-ed in the Caribbean Journal by HRRW’s Jake Johnston reads:

Less than a week after cholera began its violent spread throughout Haiti, a UN military base in the central plateau became the prime suspect for having introduced the bacteria.

The UN was quick to shoot down this theory, claiming the base met international standards. Days later, journalists found sewage tanks and latrines overflowing, with the resulting black liquid flowing into a tributary of Haiti’s largest river.

Still, the UN didn’t hesitate to defend itself; the head of the UN troops (known as MINUSTAH), said that it was “really unfair to accuse the UN for bringing cholera into Haiti.”

But the evidence kept mounting; in January 2011, a scientific journal lent further credence to the theory, in July another, and in August yet another.

Even the UN’s own investigation into the outbreak found that the UN base was the likely source, though the results were obfuscated by blaming the spread on a “confluence of factors.”

In the meantime, Haitians continued to die. By the end of January 2011, just over three months after cholera’s introduction, the official death toll was over 4,300.  All the while the U.N. maintained its innocence.

Read the rest here.

An op-ed in the Caribbean Journal by HRRW’s Jake Johnston reads:

Less than a week after cholera began its violent spread throughout Haiti, a UN military base in the central plateau became the prime suspect for having introduced the bacteria.

The UN was quick to shoot down this theory, claiming the base met international standards. Days later, journalists found sewage tanks and latrines overflowing, with the resulting black liquid flowing into a tributary of Haiti’s largest river.

Still, the UN didn’t hesitate to defend itself; the head of the UN troops (known as MINUSTAH), said that it was “really unfair to accuse the UN for bringing cholera into Haiti.”

But the evidence kept mounting; in January 2011, a scientific journal lent further credence to the theory, in July another, and in August yet another.

Even the UN’s own investigation into the outbreak found that the UN base was the likely source, though the results were obfuscated by blaming the spread on a “confluence of factors.”

In the meantime, Haitians continued to die. By the end of January 2011, just over three months after cholera’s introduction, the official death toll was over 4,300.  All the while the U.N. maintained its innocence.

Read the rest here.

865 days after Haiti’s cholera epidemic first began, with over 8,000 dead and some 650,000 sickened, the government of Haiti, with international support, officially launched a ten-year cholera eradication plan today after months of delays. The plan calls for an investment of $2.2 billion in clean water and sanitation infrastructure, with some $485.9 million needed for the next two years. Currently 31 percent of the population does not have access to potable water, while 83 percent lack access to adequate sanitation. By 2022, the plan aims to deliver potable water and improved sanitation services to 85 and 90 percent of the population, respectively.The plan notes that in the short term, “actions will focus on preventing the transmission of cholera from one person to another through the use of drinking water disinfected with chlorine, and the promotion of hand washing, good sanitary practices, and food hygiene.” Resources will also go to capacity building and training for the relevant government agencies, in particular the health ministry (MSPP) and the water agency (DINEPA). Over the long-term, some $650 million will go to DINEPA to build water supply systems in the 21 largest cities in the country, though most of this would start after the next two years. A breakdown of funding needs by sector, program and time-frame can be seen below. Overall, about 70 percent of the needed funds are to go to water and sanitation provision, though just over 10 percent of that is planned to be spent in the first two years.The objectives, in terms of cholera specifically, are to reduce the incidence rate to below 0.5 percent by 2014, below 0.1 percent in 2017 and below 0.01 percent by 2022. This compares to an incidence rate of over 1.1 percent in 2012, which translates to about 110,000 cases for that year.The plan also envisions a strengthening of the public health sector and of the coordination between NGOs and the government. To this end, the government plans to “integrate their support into the national health system.” Through investments in training, capacity building and by channeling funds through the domestic institutions in charge of each sector, the plan aims to create a stronger public sector overall. This could be especially significant given that aid for the cholera response (and for the overall relief and reconstruction effort) has largely bypassed the Haitian government. According to data from the U.N. Special Envoy, only 2.5 percent of humanitarian spending for cholera went through the Haitian government. As noted in the plan, the “lack of investment coming directly from the country’s fiscal budget represents a threat to the stability of the” water and sanitation sector.There are to be three evaluations of implementation done in 2014, 2017 and 2022 and an audit will be conducted at the half-way point and at the conclusion of the plan. Additionally, a technical committee made up of high-level representatives from relevant government agencies will meet quarterly to assess progress and propose remedies. Plan Remains Woefully UnderfundedResponding to the plans’ launch today, implementing partner PAHO’s Director Carissa F. Etienne noted that, “For the plan to be implemented, Haiti’s friends in the international community must align their efforts and harmonize around this plan and provide the necessary financial resources.” Yet thus far, meaningful support has been hard to find.
865 days after Haiti’s cholera epidemic first began, with over 8,000 dead and some 650,000 sickened, the government of Haiti, with international support, officially launched a ten-year cholera eradication plan today after months of delays. The plan calls for an investment of $2.2 billion in clean water and sanitation infrastructure, with some $485.9 million needed for the next two years. Currently 31 percent of the population does not have access to potable water, while 83 percent lack access to adequate sanitation. By 2022, the plan aims to deliver potable water and improved sanitation services to 85 and 90 percent of the population, respectively.The plan notes that in the short term, “actions will focus on preventing the transmission of cholera from one person to another through the use of drinking water disinfected with chlorine, and the promotion of hand washing, good sanitary practices, and food hygiene.” Resources will also go to capacity building and training for the relevant government agencies, in particular the health ministry (MSPP) and the water agency (DINEPA). Over the long-term, some $650 million will go to DINEPA to build water supply systems in the 21 largest cities in the country, though most of this would start after the next two years. A breakdown of funding needs by sector, program and time-frame can be seen below. Overall, about 70 percent of the needed funds are to go to water and sanitation provision, though just over 10 percent of that is planned to be spent in the first two years.The objectives, in terms of cholera specifically, are to reduce the incidence rate to below 0.5 percent by 2014, below 0.1 percent in 2017 and below 0.01 percent by 2022. This compares to an incidence rate of over 1.1 percent in 2012, which translates to about 110,000 cases for that year.The plan also envisions a strengthening of the public health sector and of the coordination between NGOs and the government. To this end, the government plans to “integrate their support into the national health system.” Through investments in training, capacity building and by channeling funds through the domestic institutions in charge of each sector, the plan aims to create a stronger public sector overall. This could be especially significant given that aid for the cholera response (and for the overall relief and reconstruction effort) has largely bypassed the Haitian government. According to data from the U.N. Special Envoy, only 2.5 percent of humanitarian spending for cholera went through the Haitian government. As noted in the plan, the “lack of investment coming directly from the country’s fiscal budget represents a threat to the stability of the” water and sanitation sector.There are to be three evaluations of implementation done in 2014, 2017 and 2022 and an audit will be conducted at the half-way point and at the conclusion of the plan. Additionally, a technical committee made up of high-level representatives from relevant government agencies will meet quarterly to assess progress and propose remedies. Plan Remains Woefully UnderfundedResponding to the plans’ launch today, implementing partner PAHO’s Director Carissa F. Etienne noted that, “For the plan to be implemented, Haiti’s friends in the international community must align their efforts and harmonize around this plan and provide the necessary financial resources.” Yet thus far, meaningful support has been hard to find.

UN’s Immunity Claim Provokes Outrage

The U.N.’s claim of immunity in response to the legal complaint filed against it on behalf of over 6,000 cholera victims has provoked outrage. Author Kathie Klarreich called it “unconscionable and immoral” in a Miami Herald op-ed yesterday, saying the U.N
The U.N.’s claim of immunity in response to the legal complaint filed against it on behalf of over 6,000 cholera victims has provoked outrage. Author Kathie Klarreich called it “unconscionable and immoral” in a Miami Herald op-ed yesterday, saying the U.N
There were two significant and possibly historic legal developments in Haiti today. After Jean-Claude Duvalier refused yet again to appear in court today, Judge Jean Joseph Lebrun issued an order for him to appear at the next hearing, meaning Duvalier wil
There were two significant and possibly historic legal developments in Haiti today. After Jean-Claude Duvalier refused yet again to appear in court today, Judge Jean Joseph Lebrun issued an order for him to appear at the next hearing, meaning Duvalier wil
In Argentina, Guatemala, Peru and other countries in the region, former dictators and many of those responsible for egregious human rights violations under former authoritarian regimes have been, or are in the process of being tried for their crimes.  In
In Argentina, Guatemala, Peru and other countries in the region, former dictators and many of those responsible for egregious human rights violations under former authoritarian regimes have been, or are in the process of being tried for their crimes.  In
On September 23, 2011 MWH Americas, previously alleged to have overcharged the city of New Orleans on reconstruction projects, was awarded a $2.8 million contract from the United States Agency for International Development (USAID) to conduct a “feasibility study of northern ports in Haiti.” The study is likely linked to the new, much touted Caracol Industrial Park in northern Haiti, which includes plans for new port facilities.Within two weeks of receiving the $2.8 million contract, MWH Americas turned around and gave out $1.45 million in subcontracts to four different firms, all headquartered in Washington DC or Virginia. MWH gave $363,540 to Nathan Associates to perform “economic and financial studies on potential port projects,” including a review “of previous studies and existing conditions.” URS Group received $438,670; the project description for that subaward is simply “feasibility study of northern ports in Haiti,” the same as is listed for MWH. Meanwhile TEC Inc. (which later became Cardno-TEC Inc.) was awarded $620,123 to provide the “Senior Port Engineer,” “Senior Environmental Specialist” and the engineering and support staff to “perform” the feasibility study. Finally, GW Consulting Inc., was given $26,932 for security and logistics. At this point, there were five U.S. firms based in the DC area working on the feasibility study, each with its own staff and associated overhead costs. Firms are allowed to allocate a percentage of their contract to headquarters to cover general operating costs of the firm; this is known as the indirect cost rate. Although this information is not disclosed (and has been redacted in contracts obtained through the Freedom of Information Act), according to those familiar with the process it is generally around 20 percent.Despite the millions already spent on the feasibility study, when the expected project completion date came, MWH was awarded $1 million to cover additional costs and the completion date was changed. Subsequently, MWH was awarded $435,000 in September 2012 and the completion date was pushed back to November 30, 2012. Since then, the completion date has been pushed back two more times and is now set for the end of February 2013. Of the additional $1.44 million awarded to MWH, they gave out some $550,000 in subcontracts. In total, as can be seen below, nearly 50 percent of the total award to MWH was spent on subcontracts to other U.S. firms. The contract with MWH Americas is, however, commendable in one way.  It is the only USAID contract in Haiti for which there is information on subcontractors, thanks to the fact that MWH actually reported their sub-awards to USASpending.gov. While MWH Americas is the only contractor to have done this, it is likely that many others are also required to do so. For example, Chemonics, the largest USAID contractor in Haiti (and the world) is required to report on their use of subcontractors, according to a copy of their contract acquired through a Freedom of Information Act request. Yet no information from any other contracts for work in Haiti appears on the USAspending.gov website. Additionally, there is legislation which now requires prime contractors to report sub-awards: the Federal Funding Accountability and Transparency Act, which was passed in 2006. Under the legislation, as of March 2011 all sub awards over $25,000 must be reported to a centralized system.
On September 23, 2011 MWH Americas, previously alleged to have overcharged the city of New Orleans on reconstruction projects, was awarded a $2.8 million contract from the United States Agency for International Development (USAID) to conduct a “feasibility study of northern ports in Haiti.” The study is likely linked to the new, much touted Caracol Industrial Park in northern Haiti, which includes plans for new port facilities.Within two weeks of receiving the $2.8 million contract, MWH Americas turned around and gave out $1.45 million in subcontracts to four different firms, all headquartered in Washington DC or Virginia. MWH gave $363,540 to Nathan Associates to perform “economic and financial studies on potential port projects,” including a review “of previous studies and existing conditions.” URS Group received $438,670; the project description for that subaward is simply “feasibility study of northern ports in Haiti,” the same as is listed for MWH. Meanwhile TEC Inc. (which later became Cardno-TEC Inc.) was awarded $620,123 to provide the “Senior Port Engineer,” “Senior Environmental Specialist” and the engineering and support staff to “perform” the feasibility study. Finally, GW Consulting Inc., was given $26,932 for security and logistics. At this point, there were five U.S. firms based in the DC area working on the feasibility study, each with its own staff and associated overhead costs. Firms are allowed to allocate a percentage of their contract to headquarters to cover general operating costs of the firm; this is known as the indirect cost rate. Although this information is not disclosed (and has been redacted in contracts obtained through the Freedom of Information Act), according to those familiar with the process it is generally around 20 percent.Despite the millions already spent on the feasibility study, when the expected project completion date came, MWH was awarded $1 million to cover additional costs and the completion date was changed. Subsequently, MWH was awarded $435,000 in September 2012 and the completion date was pushed back to November 30, 2012. Since then, the completion date has been pushed back two more times and is now set for the end of February 2013. Of the additional $1.44 million awarded to MWH, they gave out some $550,000 in subcontracts. In total, as can be seen below, nearly 50 percent of the total award to MWH was spent on subcontracts to other U.S. firms. The contract with MWH Americas is, however, commendable in one way.  It is the only USAID contract in Haiti for which there is information on subcontractors, thanks to the fact that MWH actually reported their sub-awards to USASpending.gov. While MWH Americas is the only contractor to have done this, it is likely that many others are also required to do so. For example, Chemonics, the largest USAID contractor in Haiti (and the world) is required to report on their use of subcontractors, according to a copy of their contract acquired through a Freedom of Information Act request. Yet no information from any other contracts for work in Haiti appears on the USAspending.gov website. Additionally, there is legislation which now requires prime contractors to report sub-awards: the Federal Funding Accountability and Transparency Act, which was passed in 2006. Under the legislation, as of March 2011 all sub awards over $25,000 must be reported to a centralized system.
Port-au-Prince - It “shook the house, like this” he says, violently rocking back and forth, acting it out. He yelled to his wife to get out, grabbed the children and went to the street. “Ten minutes later it was,” he said, bringing his hands together, “flat.” With this, Sonny Jean’s post-earthquake story begins; three years later we’re speaking at one of Haiti’s first sewage treatment plants, located in Titanyen.Sonny Jean, showing off the DINEPA sewage treatment plan in Titanyen; Hundreds of shelters dot the background in Kanaan.Like many of those who lost their homes, Sonny settled with his family on the Champ de Mars, the public park in downtown Port-au-Prince across from where the national palace once stood, which later became home to at least 20,000 people. Sonny lived there with his family in a small shelter and “it was tough,” he said, adding, “it wasn’t the place I wanted to raise my family.” In December of 2010, a friend tried to convince him to move to a tract of land the government had declared to be of public utility. While at first skeptical of moving so far from downtown Port-au-Prince, he knew he couldn’t stay in the Champ de Mars camp either.Eventually, he packed up his tent and what belongings had survived the earthquake and went with his wife and children to Kanaan, a vast expanse of land on a hillside about 20 km outside of Port-au-Prince. Like the majority of those who have left the camps, it wasn’t through a rental subsidy or because they were given a temporary shelter or had their home repaired. According to Sonny, he was the first to set up a tent so far west in the area, though he’s now joined by hundreds of others close by, and up to hundreds of thousands in all of Kanaan.But life there is difficult and was especially in those early days. “I was lonely, man, scared,” he said.  With the wind whipping incessantly and no other families around, there were many restless nights.Later, across the street from his new home, Sonny noticed some people starting to clear the land. He told his wife he was going to check it out; she was skeptical anything good would come of it. He went across the street, standing alone, just looking on. Eventually he heard someone, who seemed to be in charge, speaking Kreyol but “different than I speak it.” So he responded in English, which he had picked up in the years he had lived in the U.S. on a seaman’s visa. (Though he’d like to return to the U.S. someday, he hasn’t been able to get a new visa.)The manager, an English speaker from another Caribbean island, was impressed by his English, and after speaking for awhile, offered him a job on the site.It’s been many months since that chance encounter, and now, some nine months since Haiti’s second sewage treatment plant opened, he was showing the place off; the area where the trucks dump their waste water, the treatment ponds which the water filters in to, the area where they clean the trucks before they exist the plant and also where they hope to have a garden, where they can use the treated water for irrigation.
Port-au-Prince - It “shook the house, like this” he says, violently rocking back and forth, acting it out. He yelled to his wife to get out, grabbed the children and went to the street. “Ten minutes later it was,” he said, bringing his hands together, “flat.” With this, Sonny Jean’s post-earthquake story begins; three years later we’re speaking at one of Haiti’s first sewage treatment plants, located in Titanyen.Sonny Jean, showing off the DINEPA sewage treatment plan in Titanyen; Hundreds of shelters dot the background in Kanaan.Like many of those who lost their homes, Sonny settled with his family on the Champ de Mars, the public park in downtown Port-au-Prince across from where the national palace once stood, which later became home to at least 20,000 people. Sonny lived there with his family in a small shelter and “it was tough,” he said, adding, “it wasn’t the place I wanted to raise my family.” In December of 2010, a friend tried to convince him to move to a tract of land the government had declared to be of public utility. While at first skeptical of moving so far from downtown Port-au-Prince, he knew he couldn’t stay in the Champ de Mars camp either.Eventually, he packed up his tent and what belongings had survived the earthquake and went with his wife and children to Kanaan, a vast expanse of land on a hillside about 20 km outside of Port-au-Prince. Like the majority of those who have left the camps, it wasn’t through a rental subsidy or because they were given a temporary shelter or had their home repaired. According to Sonny, he was the first to set up a tent so far west in the area, though he’s now joined by hundreds of others close by, and up to hundreds of thousands in all of Kanaan.But life there is difficult and was especially in those early days. “I was lonely, man, scared,” he said.  With the wind whipping incessantly and no other families around, there were many restless nights.Later, across the street from his new home, Sonny noticed some people starting to clear the land. He told his wife he was going to check it out; she was skeptical anything good would come of it. He went across the street, standing alone, just looking on. Eventually he heard someone, who seemed to be in charge, speaking Kreyol but “different than I speak it.” So he responded in English, which he had picked up in the years he had lived in the U.S. on a seaman’s visa. (Though he’d like to return to the U.S. someday, he hasn’t been able to get a new visa.)The manager, an English speaker from another Caribbean island, was impressed by his English, and after speaking for awhile, offered him a job on the site.It’s been many months since that chance encounter, and now, some nine months since Haiti’s second sewage treatment plant opened, he was showing the place off; the area where the trucks dump their waste water, the treatment ponds which the water filters in to, the area where they clean the trucks before they exist the plant and also where they hope to have a garden, where they can use the treated water for irrigation.

CEPR’s Arthur Phillips and Stephan Lefebvre have written a nice post analyzing the World Bank and IMF’s repeatedly over-optimistic economic growth projections for Haiti over at our sister-blog, “The Americas Blog.” They note that the latest “projections of 6 percent or higher GDP growth in 2013 seem unfounded.” The institutions’ growth projections for Venezuela in recent years, by contrast, have repeatedly been overly pessimistic compared to the actual results.

CEPR’s Arthur Phillips and Stephan Lefebvre have written a nice post analyzing the World Bank and IMF’s repeatedly over-optimistic economic growth projections for Haiti over at our sister-blog, “The Americas Blog.” They note that the latest “projections of 6 percent or higher GDP growth in 2013 seem unfounded.” The institutions’ growth projections for Venezuela in recent years, by contrast, have repeatedly been overly pessimistic compared to the actual results.

The Office of the Haiti Special Coordinator under the U.S. State Department has issued a new report to the U.S. Congress as required under the Supplemental Appropriations Act of 2010. The new report covers the period of 180 days up to September 30 last year. While there are some noteworthy accomplishments, these are unfortunately few, and it is important to keep in mind the greater context of money raised, committed, disbursed and spent, as well as the urgent needs at hand. The report notes that of $2.35 billion committed to Haiti since 2010, only about 50 percent has actually been spent. Excluding debt relief, of the $900 million made available in the 2010 supplemental appropriations bill as part of the New York donor conference pledge, just 32.9 percent has been spent [PDF]. It’s also noteworthy that of the nearly $300 million committed in 2012, only about a third was even obligated. Considering that some 360,000 people are still estimated to be living in IDP camps three years after the earthquake, the report of “over 900 seismic and hurricane resistant houses under construction in Caracol, Northern Haiti and in Cabaret north of Port-au-Prince” seems relatively insignificant, not to mention the figure of “227 Haitian beneficiaries…selected to receive housing” “to date.” This is even less impressive considering that the sprawling U.S. Embassy compound in Port-au-Prince “consists of 107 new [three to five bedroom] townhouse units and a new Deputy Chief of Mission residence, along with support facilities, including a recreation center with an outdoor pool and courts, for two separate compounds,” according to the architectural firm that the State Department contracted to design it. The report similarly mentions “250 LPG commercial stoves were sold to large charcoal users (street food vendors and schools) in Port-au-Prince” and four “Haitian small- and medium-size enterprises” that “won matching grants” in a “business plan competition.” The report is also notable for what it does not mention: cholera, for example. This is a word and topic that does not appear once in the report, despite the ongoing epidemic and despite that “Health and Other Basic Services” is “Pillar C” of USAID’s “Haiti Rebuilding and Development Strategy.” Pillar C is allotted three paragraphs of the report; cholera is arguably Haiti’s most urgent humanitarian crisis, killing more people every day.
The Office of the Haiti Special Coordinator under the U.S. State Department has issued a new report to the U.S. Congress as required under the Supplemental Appropriations Act of 2010. The new report covers the period of 180 days up to September 30 last year. While there are some noteworthy accomplishments, these are unfortunately few, and it is important to keep in mind the greater context of money raised, committed, disbursed and spent, as well as the urgent needs at hand. The report notes that of $2.35 billion committed to Haiti since 2010, only about 50 percent has actually been spent. Excluding debt relief, of the $900 million made available in the 2010 supplemental appropriations bill as part of the New York donor conference pledge, just 32.9 percent has been spent [PDF]. It’s also noteworthy that of the nearly $300 million committed in 2012, only about a third was even obligated. Considering that some 360,000 people are still estimated to be living in IDP camps three years after the earthquake, the report of “over 900 seismic and hurricane resistant houses under construction in Caracol, Northern Haiti and in Cabaret north of Port-au-Prince” seems relatively insignificant, not to mention the figure of “227 Haitian beneficiaries…selected to receive housing” “to date.” This is even less impressive considering that the sprawling U.S. Embassy compound in Port-au-Prince “consists of 107 new [three to five bedroom] townhouse units and a new Deputy Chief of Mission residence, along with support facilities, including a recreation center with an outdoor pool and courts, for two separate compounds,” according to the architectural firm that the State Department contracted to design it. The report similarly mentions “250 LPG commercial stoves were sold to large charcoal users (street food vendors and schools) in Port-au-Prince” and four “Haitian small- and medium-size enterprises” that “won matching grants” in a “business plan competition.” The report is also notable for what it does not mention: cholera, for example. This is a word and topic that does not appear once in the report, despite the ongoing epidemic and despite that “Health and Other Basic Services” is “Pillar C” of USAID’s “Haiti Rebuilding and Development Strategy.” Pillar C is allotted three paragraphs of the report; cholera is arguably Haiti’s most urgent humanitarian crisis, killing more people every day.

Want to search in the archives?

¿Quieres buscar en los archivos?

Click Here Haga clic aquí